Our Projects work with LARSEN & TOUBRO LIMITED

Fabrication and Erection of Pipeline Oxygen/Steam Line Vessel area work at Tata Steel Ltd. Jamshedpur.

Fabrication and Erection of Pipeline Oxygen/Steam Line Vessel area work at Tata Steel Ltd. Jamshedpur.
Project : LD #3
Employer : TATA STEEL LIMITED
LARSEN & TOUBRO LIMITED
E237 Dt:20.10.2011

Erection & Commissioning of Slab Caster (Including Equipment, Technological Structure, Pipe Line Works) at Bokaro Steel Plant, Bokaro

Erection & Commissioning of Slab Caster (Including Equipment, Technological Structure, Pipe Line Works) at Bokaro Steel Plant, Bokaro
Project : Continuous Casting Plant
Employer : SAIL - Bokaro Steel Plant
LARSEN & TOUBRO LIMITED
L&T/BSL/044 Dt: 03.06.2017

Fabrication & Erection of Steel Structure for Conveyor Galleries & Junction Houses at Hindustan Zinc Limited, Rajasthan

Fabrication & Erection of Steel Structure for Conveyor Galleries & Junction Houses at Hindustan Zinc Limited, Rajasthan
Project : HZL Expansion Work
Employer : Hindustan Zinc Limited (Vedanta Group)
LARSEN & TOUBRO LIMITED
EG564WOR7000064 Dt: 14.11.2017

© Copyright 2017-2019 UK Group All rights reserved